# Project State
|
|
|
|
## Project Reference
|
|
|
|
See: .planning/PROJECT.md (updated 2026-04-04)
|
|
|
|
**Core value:** Detect leaked LLM API keys across more providers and more internet sources than any other tool, with active verification to confirm keys are real and alive.
|
|
**Current focus:** Phase 1 — Foundation
|
|
|
|
## Current Position
|
|
|
|
Phase: 1 of 18 (Foundation)
|
|
Plan: 0 of ? in current phase
|
|
Status: Ready to plan
|
|
Last activity: 2026-04-04 — Roadmap created, 18 phases defined covering 146 v1 requirements
|
|
|
|
Progress: [░░░░░░░░░░░░░░░░░░░░] 0%
|
|
|
|
## Performance Metrics
|
|
|
|
**Velocity:**
|
|
- Total plans completed: 0
|
|
- Average duration: —
|
|
- Total execution time: 0 hours
|
|
|
|
**By Phase:**
|
|
|
|
| Phase | Plans | Total | Avg/Plan |
|
|
|-------|-------|-------|----------|
|
|
| - | - | - | - |
|
|
|
|
**Recent Trend:**
|
|
- Last 5 plans: —
|
|
- Trend: —
|
|
|
|
*Updated after each plan completion*
|
|
|
|
## Accumulated Context
|
|
|
|
### Decisions
|
|
|
|
Decisions are logged in PROJECT.md Key Decisions table.
|
|
Recent decisions affecting current work:
|
|
|
|
- Roadmap: CGO_ENABLED=0 throughout — modernc.org/sqlite over mattn/go-sqlite3 (see PROJECT.md)
|
|
- Roadmap: Per-source rate limiter architecture (Phase 9) must precede all OSINT source modules (Phases 10-16)
|
|
- Roadmap: AES-256 encryption added in Phase 1, not post-hoc — avoids migration complexity
|
|
- Roadmap: Verification (Phase 5) requires consent prompt + LEGAL.md — not optional polish
|
|
|
|
### Pending Todos
|
|
|
|
None yet.
|
|
|
|
### Blockers/Concerns
|
|
|
|
- Phase 1: Argon2 vs PBKDF2 for database encryption key derivation — needs decision before Storage Layer implementation
|
|
- Phase 1: Aho-Corasick library choice (cloudflare/ahocorasick vs bobrik/ahocorasick) — verify which TruffleHog uses
|
|
- Phase 2+: Provider YAML patterns for 108 providers — lesser-known providers need targeted research (Chinese LLMs, niche APIs)
|
|
- Phase 11: Google Custom Search API quota (100 queries/day free tier) vs direct scraping ToS trade-off — product decision needed
|
|
|
|
## Session Continuity
|
|
|
|
Last session: 2026-04-04
|
|
Stopped at: Roadmap written to .planning/ROADMAP.md; ready to begin Phase 1 planning
|
|
Resume file: None
|